Monday, June 17, 2013
8:00 – 8:05 a.m. Opening Remarks - Kieffer
8:05 – 9:35 a.m. Introduction to Grouting - Warner
- Brief History
- Why Grout?
- Fundamentals of pressure and injection rate
- Types of Injection Systems
- Risks
9:50 – 11:50 a.m. Types of Grout and Grout Rheology - Warner/Goodwin
- Viscosity
- Wetability/Affinity
- Thixotropy
- Settlement/Bleed
- Temperature effects
- Mixing energy
11:50 – 1:00 p.m. Lunch
1:00 – 1:50 p.m. Hydraulic Cement Grout Additives - Goodwin/Warner
- Calcium Silicate Cements
- Calcium Aluminate Cements
- Expansive or Shrinkage Compensating Cements
- Other Cements
- Hybrid Binders
- Fillers and Aggregates
- Pozzolans
- Accelerators
- Retarders and Hydration Control Agents
- Water Reducers, Dispersants, and Superplasticizers
- Water Retention and Anti-Bleeding Additives
- Fibers
- Viscosifiers
- Suspending Agents
- Anti washout Additives
- Pumping Aids
- Gas Generating Agents
- Air Entrainment and Foaming Agents
- Latex or Polymer Dispersions
1:55 – 3:55 p.m. Limited Mobility Grouting - Warner
- Void filling
- Forming structural members
- Compaction grouting
- Grout Holes
- Pump requirements
4:05 – 5:05 p.m. Compaction Grouting- Harris
- Injection sequence
- Refusal criteria
- Monitoring/Records
- Examples of use
5:05 – 6:30 p.m. Icebreaker Reception
Tuesday, June 18, 2013
8:00 – 10:00 a.m. Chemical Solution Grout Materials and Applications - Iske
- Solution grout types
- Thickening models
- Silicates
- Acrylamides
- Acrylates
- Urethanes
- Epoxies
10:10 – 11:00 a.m. Engineering Geologic Considerations for Rock Mass Grouting - Kieffer
11:05 a.m. – 12:05 p.m. Cement Grouting in Rock I - Dreese
- Typical applications
- Grouted cutoffs for seepage reduction
- Objectives
- When is grouting necessary
- Typical hole layouts and orientations
- Split spacing of holes
- Consolidation grouting
- Objectives
- Typical hole layouts
- Grout caps
- Operations and sequence
- Layout and marking of holes
- Drilling - upstage versus downstage
12:05 – 1:05 p.m. Lunch
1:05 – 2:05 p.m. Cement Grouting in Rock I (continued) - Dreese
- Hole washing
- Water testing
- Mixing of grout
- Grout injection
- Grouting equations of interest
- Managing grout application
- Final check of equipment
- Starting mixes
- Grout pressures - rules of thumb
- Are high pressures necessary?
- Grouting the hole
- Mix changes during grouting (thickening)
- Assessment of grouting - quality assurance
- Relationship between water tests and cement takes
- Contract bid items
2:15 – 3:15 p.m. Cement Grouting in Rock II - The GIN (Grouting Intensity Number) Method - Gazzarrini
- GIN Method Concepts
- Pressure/Volume in grouting
- Water Pressure Tests
- Theory behind the method
- Practical examples
- Case Histories
3:20 – 4:20 p.m. Cement Grouting in Rock (III) - Aperture Controlled Grouting - Carter
- Distinction and Definitions - GIN and ACG
- Discrete Fracture Networks
- Fracture Characterization
- Grout Protocol Development
- Decision Flow Chart
- Mix Sequencing
- Injection Control
- Monitoring Systems
- Field Procedure Guidelines
- Closure Criteria and Verification
4:25 – 5:10 p.m. Quantitative Design of Grout Curtains - Dreese
Wednesday, June 19, 2013
8:00 – 8:50 a.m. Computer Controlled Grouting & Advantages of Stable Grouts - Dreese
8:55 – 9:55 a.m. Case Histories - Dam Remediation Projects - Dreese
10:05 – 12:00 a.m. Jet Grouting - Burke
- Introduction
- Terms and Definitions
- History and Development
- Applications of Jet Grouting
- Jet Grouting Systems
- Applications of Jet Grouting
- Single Fluid System
- Double Fluid System
- Triple Fluid System
- Cross-Jetting
- Super-Jet
- System(s) Selection
- Case Histories
12:45 p.m. – 5:00 p.m. Field Demo at Baski, Inc. (with lunch) - Warfield, et. al.
Thursday, June 20, 2013
8:00 – 8:30 a.m. Foaming Agents - Palladino
8:35 – 9:20 a.m. Grouting Equipment and Maintenance - Warfield
9:25 – 9:45 a.m. Jet grouting at the Zeballos Lake IPP, Vancouver, B.C. - Gazzarrini
9:50 – 10:45 a.m. Evolution of Drilling Practices - Bruce
- Drilling methods
- Drilling equipment
- Driving grout casing
- Circulation flush
- Drill bits
- Grout caps
10:50 – 11:30 a.m. Rock Anchors - Bruce
- Terminology, definitions & classification
- Applications, design and construction
- Stressing and testing
- Corrosion protection
- New developments
- Standards, recommendations & sources of data
- Illustrated case histories
11:30 a.m. – 12:15 p.m. Micropiles - Bruce
- Terminology, characteristics and classification
- Applications, design, and construction
- Stressing and testing
- Corrosion protection
- New developments
- Standards, recommendations & sources of data
- Illustrated case histories
12:15 – 1:00 p.m. Lunch
1:00 – 2:00 p.m. Cutoff Walls - Bruce
2:10 – 2:40 p.m. Composite Walls - Bruce
2:40 – 3:10 p.m. Crisis Management - Bruce
3:20 – 5:15 p.m. Permeation Grouting of Soils - Warner
- Soil Solidification/Strengthening
- Increasing natural frequency
- Water Control
- Injection modes and methods
- Grout Holes
- Examples of use
Friday, June 21, 2013
8:00 – 9:30 a.m. Grouting Instrumentation - Choquet
9:40 – 10:25 a.m. Grouting in Underground Construction - Kieffer
- Pre-Excavation Grouting
- Backfill Grouting
- Contact Grouting
- Pressure Tunnels - Pre-Stressing with the TIWAG Gap Grouting Method
10:30 a.m – 12:00 p.m. Pre-Excavation Grouting in Rock- Hognestad
12:00 – 1:00 p.m. Lunch
1:00 – 1:50 p.m. Tunnel Grouting – Contractor Considerations - Wimmer/Kofoed
- Specifications
- Lump sum vs. Unit Price
- Risk Analysis
- Real Jobs: Estimating and Construction lessons learned
2:00 – 2:55 p.m. Slab Jacking/Grout Jacking - Harris
- Grout Holes
- Grout type and consistency
- Injection sequence
- Monitoring and controls
- Examples of use
3:00 – 4:00 p.m. Structural Grouting - Warner
- Defects in concrete
- Voids/honeycomb
- Masonry voids
- Base plates/Machinery bases
- Vacuum Grouting
- Underwater Grouting
- Preplaced Aggregate Concrete
4:00 – 4:45 p.m. Grouting Case Histories - Bandimere